Back to overview
Residential construction

Dresden
Schützengarten

Dresden, Germany / 04.2021 - 09.2024

PORR building construction Region Ost developed the “Schützengarten” residential estate in the immediate vicinity of Dresden city centre. Commissioned by BauBeCon Wohnwerte GmbH, the project comprised 19 residential blocks with a total of 403 flats, commercial space as well as two underground car parks with 193 parking spaces. As the main contractor, PORR was responsible for the turnkey construction, including the detailed design. PORR Spezialtiefbau carried out the special civil engineering works.

The picture shows the Schützengarten as seen from the village of Drohnen. The entire area can be seen.
© PORR

Facts & Figures


Company

PORR GmbH & Co. KGaA

Type

Residential construction, Commercial building, Office buildings

Runtime

04.2021 - 09.2024

Principal
BauBeCon Wohnwerte GmbH

Schützengarten residential estate in Dresden

Residential and commercial buildings near Dresden city centre

The 19 buildings were constructed in two phases and comprise a total of around 28,950 m² of residential floor space. In addition, around 1,969 m² of commercial buildings were created for restaurants, offices and retail outlets. The four- to seven-storey residential buildings are grouped around, amongst other things, landscaped courtyards and together form the new quarter.

From dismantling to a new residential quarter

Before construction began, the existing buildings dating from the 1980s were dismantled. This included two eight-storey office blocks, a former canteen as well as a Cold War-era bunker.

Around 4,300 t of concrete from the dismantling was processed and subsequently reused to backfill the construction pits as well as in road construction. This meant that some of the existing material remained in use within the construction project.

Building Construction and Special Civil Engineering in a Single Project

Whilst PORR Special Civil Engineering created the conditions for the subsequent development, PORR Building Construction Region East was responsible for the turnkey construction of the building complex. The work carried out by the various specialist departments thus interlinked across several construction phases.

A New Urban Landmark in a Historic Location

With the Schützengarten, the site – previously used for other purposes – between Dresden city centre and the neighbouring urban districts has been given a new function. The combination of flats, commercial spaces, underground car parks and green internal areas further develops the site into a mixed-use quarter. The dismantling of the former buildings and the subsequent new development mark two closely interlinked phases in the site’s development.

PORR Germany . Schützengarten, Dresden - Impressions in 30 seconds

What ultimately counts in the construction business is successfully completed projects. PORR has many of these.