Osram Production Hall

Regensburg-Burgweinting,, Germany / 09.2006 - 02.2008

In 2006 the consortium “Arge Osram, 3. Bauabschnitt” with PORR GmbH & Co. KGaA, Munich, won the tender for the turnkey construction of the production facility Osram Regensburg-Burgweinting with a gross floor area of 25,000m2. The project included the third construction phase and the technical infrastructure inside and outside the building, excluding building services equipment.

Produktionshalle Osram 01

Facts & Figures


Company

PORR GmbH & Co. KGaA Building Construction in a consortium

Type

Industrial construction

Runtime

09.2006 - 02.2008

Principal
Osram Opto Semiconductors GmbH

High-tech site in Regensburg.

All of the parts of the building were constructed without a basement using monolithic reinforced concrete slabs 80 to 150cm thick.