CCG North Logistics Centre
Wundschuh, Austria / 01.2024 - 03.2025
With the construction of the new CCG Nord logistics centre in Wundschuh, Cargo-Center-Graz is expanding its infrastructure for modern logistics and distribution processes. As the total contractor, PORR AG was responsible for the planning and implementation of the large-scale logistics hall, including office areas, underground infrastructure and extensive outdoor facilities.
Facts & Figures
Company
PORR Bau GmbH
Type
Industrial construction, Facade construction, Steel construction
Runtime
01.2024 - 03.2025
Modern and sustainable logistics hall in Wundschuh
The CCG Nord logistics centre – Hall A at the Wundschuh site in Styria is a state-of-the-art logistics facility for Cargo-Center-Graz Betriebsgesellschaft m.b.G. & Co KG. PORR implemented the project as the total contractor between January 2024 and March 2025, responsible for all construction work from the structural design to the outdoor facilities.
At the heart of the project is a large-scale warehouse and logistics hall with integrated office space, complemented by ancillary buildings and extensive infrastructure. The building was constructed using a skeleton structure made of precast reinforced concrete elements and finished with a horizontal sandwich panel façade. Due to the size of the building, two approximately 80-metre-long underground escape tunnels were also constructed using in-situ concrete. Central technical facilities such as the technical and sprinkler control centre are also located in the basement.
A key element of the project is the approximately 50,000 m² jointless monolithic floor slab, which was specially designed to meet the high demands of modern logistics processes. The facility was also equipped with extensive building services, including a sprinkler system, smoke extraction system, pressure ventilation system and fire alarm system to ensure the highest safety standards. The outdoor facilities were also comprehensively constructed: a total of around 21,500 m² of double-layer asphalt surfaces were created for traffic and logistics areas. In the course of the asphalting work, 206 shafts were also raised and adjusted to the final level.
Green and LEAN for greater efficiency
Particular attention was paid to sustainable construction: all roof areas were designed with extensive green roofing and at the same time prepared for a future photovoltaic system.
The logistics hall was constructed in a phased manner. While flat roof and façade work had already begun on one part of the building, the supporting structure was still being erected at the other end. These parallel and staggered work steps enabled an optimised construction process and a significantly shorter overall construction time.
To ensure efficient project management, PORR consistently relied on LEAN construction methods, which optimised construction processes, made efficient use of resources and enabled deadlines to be reliably met.