LKH Feldkirch Reconstruction East outdoor area
Feldkirch, Austria / 09.2021 - 01.2023
The outdoor facilities of the LKH Feldkirch main entrance east were completed at the beginning of 2023 and represented a versatile construction site. Among other things, approx. 70m of prefabricated concrete benches were moved, 700m² of coloured asphalt was laid and 150m of drainage pipes were dug and laid. The realisation of this work was challenging,
Facts & Figures
Company
Nägele Hoch- und Tiefbau GmbH
Type
Road construction, Outdoor facilities
Runtime
09.2021 - 01.2023
Comprehensive civil engineering works at LKH Feldkirch
as a tight schedule had to be adhered to and close cooperation with other companies and trades was required. Ensuring access to the hospital for emergencies was always a particular priority. Despite these challenges, the project was successfully completed.