Geothermal plant in Hard
Hard, Austria / 04.2026 - 06.2026
Between April and June 2026, Nägele Hoch- und Tiefbau GmbH constructed a modern geothermal system for Rhomberg Bau GmbH at the Hofsteigstraße residential complex in Hard. The project contributes to the energy supply of the new building and utilises geothermal energy as a renewable energy source.
Facts & Figures
Company
Nägele Hoch- und Tiefbau GmbH
Type
Geothermal energy
Runtime
04.2026 - 06.2026
Efficient heat from the ground
The core of the execution involved the installation of a high-performance geothermal probe system comprising a total of ten duplex geothermal probes with a diameter of 32 millimetres. The total probe length of around 1,135 metres enables the energy stored underground to be utilised and lays the foundation for economical building operation.
The execution of the necessary flushed drilling presented the project team with particular challenges. Demanding geological conditions required the utmost precision in the planning and execution of the drilling work. Thanks to extensive experience in the field of geothermal energy and deep drilling technology, the job was completed on schedule.
The scope of work undertaken by Nägele Hoch- und Civil Engineering GmbH encompassed not only the drilling work itself, but also the complete distribution system, including all necessary connections and technical components. In addition, the necessary applications to the authorities and approval procedures were coordinated and managed. As a result, the employer received all services from a single source and benefited from seamless project management.