Industrial construction

Egger factory

Radauti, Suceava County, Romania / 08.2006 - 08.2007

Back in 2006 and 2007, the entire construction site for the Egger chipboard factory in Radauti was in the hands of PORR Construct S.R.L. Our specialist team was in charge of earthworks, civil engineering, sewerage and road construction works as well as the relocation of one river bed.


The sheer amount of the completed work might be best presented by the following figures:

Built-up area: 230,000m²
Asphalt: 80,000m²
Humus erosion: 168,000m2

Photo: well-lit, brand-new factory, machines and containers on the sides; in the middle two workers viewed from the back walking away and wearing PORR-branded working clothes and a safety jacket; on the right side, a car covered in dust and gateways; at the top, ceiling with lamps

Facts & Figures


Company

Type

Industrial construction

Runtime

08.2006 - 08.2007

Principal
Egger Romania S.R.L., STEAG encotec GmbH, Essen (D)

Construction of a factory.

Earthmoving and landfill: 105,000m3
Soil stabilisation (40cm): 85,000m2
Dirt cover first layer (25cm): 96,000m2
Concrete pipes (DN 700 to DN 1,800): 700m
Bituminous base course: 2,000t

What ultimately counts in the construction business is successfully completed projects. PORR has many of these.