Linz, Austria / 07.2015 - 10.2015

In the area of the CC8 continuous casting plant at the voestalpine steelworks in Linz, an 80cm-thick diaphragm wall with deep foundations was to be installed down to a depth of up to 19m. The jet grouting method was used to create the deep foundations in the area of the gantry crane supports. In total, PORR installed some 4,500m² of diaphragm wall using heavily reinforced cages with an overall weight of 455t (up to 220kg/m²). 

Photo: Diaphragm wall in the steelworks – side view of the building site in the existing factory hall; on the left of the photo: a construction crane

Facts & Figures


Company

PORR Bau GmbH

Type

Special civil engineering

Runtime

07.2015 - 10.2015

Principal
voestalpine AG

Firmly founded in the soil ...

One of this project’s greatest challenges lay in the fact that trenching had to take place at restricted heights in the plant/industrial production area.

What ultimately counts in the construction business is successfully completed projects. PORR has many of these.