In this project, ÖBA was commissioned with soil improvements over an area of more than 1 million m² and the manufacture of a base course stabilised with cement (BC-C) on approximately 164.000 m². The works were implemented using the in-place mixing technique.

Photo: evenly coated, light sand on a stretch of road; transportation and special construction vehicles on it; in the background, green plains and wind turbines

Facts & Figures


Company

ÖBA – Österreichische Betondecken Ausbau GmbH

Type

Concrete slab construction

Principal
ARGE A5 BL05 – Hochtief/ALPINE CZ

Für eine stabile Basis.

Over the course of the soil improvements, ÖBA installed a total of 10,000 t of chalk-cement mixture with a performance of 10,000 m² per workday and a cutting depth of 30 cm. The BC-C was carried out with a cutting depth of 20 cm on an area of 164,000 m².

In the process, 4,250 t of cement were processed. The work performance was 9,000 m² per working day.

Due to the less than ideal grain size distribution of the material to be stabilised, compliance with the short construction time was a particularly enormous challenge. For this reason, ÖBA used two recyclers at the same time. For this to work, the deliveries of the binding material had to be organised precisely – another challenge that the ÖBA team mastered perfectly in this extensive project.

Further Facts
A5 Weinviertel motorway

Service duration
04.2017 - 10.2017

What ultimately counts in the construction business is successfully completed projects. PORR has many of these.