Vienna, Austria / 07.2011 - 10.2011
This project mainly involved the reconditioning of the road construction, the entire road drainage and the entire street lighting in the area of the Auhof junction of the A1 Westautobahn motorway from km 9.5 to km 8.6 (from Vienna) and the repair of a bridging object. Here, the traffic on the main carriageway of the A1 and the entry and exit ramps had to be maintained without interruption.
Facts & Figures
Company
TEERAG-ASDAG GmbH, Lower Austria branch
Type
Bridge construction, Road construction
Runtime
07.2011 - 10.2011
Reconditioning of Vienna’s west motorway entrance slip road.
Another challenge was the short construction period of only 13 weeks for this project. To ensure both, the maintenance work was carried out in day and night shifts in three traffic phases per carriageway orientation.